I created some tasks in an event. When I try to assign them to a member, the assignment field stays empty after clicking on the submit button. Screenshots attached.
Seems to be a database update issue. Has anybody created assignments in tasks and tried to edit them? Waht happens to the assignments on your systems, do they get updated?
I just wanted to add that on first creation of a task the module assigned the task to the creator correctly, but when editing the task and assigning it to another person(s), it doesn't save the newly assigned member(s).
Unfortunately, assignee doesn't show up in the Assignments field. Additionally, once assigned, I cannot delete assignees anymore. If I delete one or more and save, the assigned members are still in the assignee list of the form.
Tasks list in container element (here events) doesn't get updated neither.
T
Seems to be a database update issue. Has anybody created assignments in tasks and tried to edit them? Waht happens to the assignments on your systems, do they get updated?
Thank you for the report - https://github.com/unaio/una/issues/4220
T
I just wanted to add that on first creation of a task the module assigned the task to the creator correctly, but when editing the task and assigning it to another person(s), it doesn't save the newly assigned member(s).
T
Dear @Alex T⚜️ ,after update to 13RC3:
Assignee gets saved now.
Unfortunately, assignee doesn't show up in the Assignments field. Additionally, once assigned, I cannot delete assignees anymore. If I delete one or more and save, the assigned members are still in the assignee list of the form.
Tasks list in container element (here events) doesn't get updated neither.
Edit: Notifications work for the assignments.
Thank you for the testing and reporting it back:
https://github.com/unaio/una/issues/4255
T
Thank you for taking care of it.
hello @thomlin , fixed in https://github.com/unaio/una/issues/4255
T
Thank you so much, Roman!